With these elements charged, KTL is already generating 55.55% revenue in tariffs.Sterlite Power, a power transmission player, has commissioned 765 kV Khandwa substation in Madhya Pradesh. The project is part of the Khargone Transmission (KTL) project.
The project will help in stepping down the high voltage 1,320 MW power from Khargone power plant to further distribute it downstream to 50 million households across the states of Madhya Pradesh, Maharashtra and Gujarat.
The company has so far commissioned five out of six elements in the project — 765 kV substation at Khandwa, 765 kV DC Khandwa-Indore transmission line, 400 kV DC Khandwa-Khargone transmission line, 400 kV line in line out (LILO) and Dhule bay extension.
With these elements charged, KTL is already generating 55.55% revenue in tariffs.
Sterlite Power had won Rs 1,370 crore Khargone Transmission project in 2015 through tariff-based competitive bidding process and is executing it under the build, own, operate and maintain (BOOM) model.
Source: ConstructionWeek online
You may also like
-
IN-SPACe Selects Three Indian Space Companies to Develop Indigenous Satellite-Based 3D City Mapping Technology
-
India’s Solar Power Capacity Reaches 175 GW, Expanding 62-Fold Since 2014
-
Hathor Rockets Plans ₹250 Crore Rocket Engine Manufacturing and Testing Facility in Andhra Pradesh
-
Waaree Energies Commissions 5.15 GWh Battery Pack Manufacturing Line in Gujarat
-
IG Defence Signs MoU for 200-Acre Indigenous Missile Manufacturing Complex in Andhra Pradesh