Wind Power Projects of 12,162.50 MW Capacity awarded so far

Juniper Green Expands Renewable Portfolio as Wind-Battery Project Reaches 177.6 MWp

The overall project is planned with 232.4 MWp of renewable generation capacity and approximately 201 MWh of battery energy storage, meaning a substantial majority of the planned generation capacity has now entered operation. The latest addition leaves approximately 54.8 MWp of planned generation capacity yet to be commissioned if the project is completed according to its currently disclosed configuration.

Indian renewable-energy producer Juniper Green Energy Limited has commissioned an additional 12.4 MW of wind power capacity, advancing the development of a large firm and dispatchable renewable-energy project that combines renewable generation with battery storage to provide electricity more reliably than conventional standalone wind or solar plants.

The new capacity has been commissioned through Juniper Green Stellar Private Limited, a wholly owned subsidiary of Juniper Green Energy. The company disclosed the development on September 1, 2026, saying that the additional wind capacity forms part of a 120-MW Firm and Dispatchable Renewable Energy, or FDRE, project. Following the latest commissioning, operational generation capacity associated with the project has increased to 177.6 MWp, accompanied by approximately 201 MWh of battery energy storage.

The overall project is planned with 232.4 MWp of renewable generation capacity and approximately 201 MWh of battery energy storage, meaning a substantial majority of the planned generation capacity has now entered operation. The latest addition leaves approximately 54.8 MWp of planned generation capacity yet to be commissioned if the project is completed according to its currently disclosed configuration.

120 MW of Firm Power Requires Much More Generation Capacity

The difference between the project’s 120-MW contracted capacity and its 232.4-MWp planned generation capacity reflects the way firm and dispatchable renewable-energy projects are designed.

A conventional 120-MW power plant based on coal or gas can, subject to operating conditions, generate electricity when required. Wind and solar plants behave differently because their output depends on weather and the availability of sunlight or wind. A 120-MW solar plant therefore cannot continuously provide 120 MW throughout the day and night.

FDRE developers address this limitation by installing substantially more renewable-generation capacity than the contracted power-delivery requirement and combining different sources of renewable electricity with energy storage.

Juniper Green Stellar’s project consequently has a contracted capacity of 120 MW but is designed around 232.4 MWp of generation capacity together with around 201 MWh of battery storage. The additional renewable capacity can generate electricity when resources are available, while batteries can store part of that energy and release it during periods when production falls or the electricity is needed at specified times.

This configuration represents an important evolution from the first phase of India’s renewable-energy expansion, when solar and wind projects were principally designed to inject whatever electricity they could generate at a particular moment into the grid.

Battery Storage Changes How Renewable Power Can Be Delivered

The approximately 201-MWh Battery Energy Storage System, or BESS, is central to the project rather than simply an auxiliary installation.

A battery with an energy capacity of 201 MWh can store electricity produced during periods of strong renewable generation and discharge that electricity later. The precise duration for which it can supply power depends on its discharge rate. For example, supplying 100 MW would theoretically consume 200 MWh of stored energy in roughly two hours, although actual usable energy depends on operating limits, efficiency and reserve requirements.

This ability to move electricity from one period of the day to another helps overcome one of the fundamental limitations of renewable power. Solar generation is strongest during daylight hours and disappears after sunset, while wind output can change considerably depending on weather conditions.

Battery storage allows excess generation to be captured instead of immediately exported or curtailed. That stored energy can then help maintain contracted supply when renewable production declines or electricity demand increases.

The resulting power profile is considerably more predictable than that produced by an isolated wind or solar installation.

Project Awarded Under SJVN’s FDRE Programme

The 120-MW project traces its origins to the SJVN competitive tender for 1,500 MW of firm and dispatchable renewable power from interstate transmission system-connected renewable projects with energy storage.

SJVN awarded Juniper Green Energy two capacities under the programme, including 200 MW in November 2023 and an additional 120 MW in December 2023. Official SJVN tender records confirm the separate 120-MW award to Juniper under the FDRE-1 programme.

Juniper Green Stellar subsequently became the project company responsible for development. Earlier company disclosures showed a Power Purchase Agreement dated April 30, 2024, with SJVN for the 120-MW contracted capacity at a tariff of ₹4.38 per kWh and a PPA tenure of 25 years.

The long-duration agreement gives the project a defined buyer and electricity tariff while requiring Juniper to satisfy the delivery obligations associated with an FDRE contract.

Such arrangements are becoming increasingly important as utilities seek renewable electricity that can contribute to the grid during specified periods rather than receiving power only whenever weather conditions allow renewable plants to generate.

Firm and Dispatchable Renewable Energy Represents the Next Stage of India’s Green Transition

India has installed large quantities of solar and wind power during the past decade, but increasing renewable penetration creates a new challenge for the electricity system.

Solar panels can produce enormous quantities of electricity during sunny afternoons, yet household and commercial electricity demand often remains high after sunset. Wind generation can complement solar output, but wind conditions are inherently variable and cannot be controlled by grid operators.

Traditional thermal and hydroelectric plants have historically provided the flexibility required to balance these variations. As renewable energy accounts for a larger proportion of electricity generation, the grid increasingly requires clean-energy projects capable of delivering a more predictable output.

FDRE projects attempt to provide that capability by combining solar generation, wind power, battery storage and sophisticated power-management systems.

Solar and wind can also complement one another. Solar production follows the daylight cycle, while wind generation can remain available during evening, night or seasonal periods when solar output is weaker. Batteries provide an additional layer by storing electricity and shifting its delivery across time.

The combination can therefore produce a much smoother and more controllable electricity profile than either renewable source could achieve independently.

Juniper Green Building Experience in Large-Scale FDRE

The latest commissioning forms part of a much broader move by Juniper Green Energy into hybrid renewable projects and battery storage.

The company says its portfolio now encompasses solar, wind, wind-solar hybrid, FDRE and battery-energy-storage projects, supported by internal engineering, procurement, construction, operations and maintenance capabilities. As of August 27, Juniper reported a total renewable portfolio of approximately 11,216 MWp across 52 projects in four Indian states.

This included roughly 2,575 MWp of operational generation capacity and 503 MWh of operational battery storage immediately before the latest commissioning update. The company also had approximately 3,562 MWp and 3,586 MWh of contracted projects under construction, in addition to a much larger awarded pipeline.

Following the September 1 commissioning, Juniper told the stock exchanges that the combined operational capacity of the company and its subsidiaries had increased to approximately 2,588 MWp, alongside around 500 MWh of operational BESS capacity. The minor difference between the storage numbers reported on different dates reflects rounding in the company’s disclosures.

The addition of only 12.4 MW may appear modest compared with Juniper’s multi-gigawatt portfolio, but its importance lies in the type of capacity being commissioned. FDRE projects incorporate substantially greater engineering and operational complexity than straightforward solar installations.

Juniper Has Already Begun Commissioning a Major FDRE System in Rajasthan

Juniper Green’s wider FDRE programme has already produced a notable industry milestone. In April 2026, the company announced that it had started commissioning what it described as India’s first FDRE project developed under the Government of India’s 2023 FDRE guidelines.

That larger integrated system combines approximately 259 MWp of solar power, 280 MW of wind generation and 200 MWh of battery storage, with assets spanning Rajasthan and Gujarat. The project is designed to deliver firm renewable electricity instead of relying solely on intermittent generation.

The company identified Fatehgarh in Barmer district, Rajasthan, as a major project location and said the power would be supplied under SJVN’s FDRE programme. Juniper described the commissioning as a shift from merely producing renewable electricity towards delivering renewable power according to grid demand.

The September 1 capacity addition demonstrates that the company’s storage-backed renewable portfolio continues to move progressively from construction into operation.

India’s Renewable Market Moving Beyond Solar and Wind Capacity Numbers

For much of India’s renewable-energy expansion, industry progress was measured principally in megawatts of solar panels or wind turbines installed.

That measure remains important, but the next phase requires increasing attention to when electricity is generated and whether it is available when consumers actually require it.

A gigawatt of solar power operating at midday cannot automatically replace a gigawatt of conventional generation required during the evening peak. Likewise, an electricity system containing very high levels of variable wind and solar generation must maintain sufficient flexibility to respond rapidly when weather changes.

Energy storage, hybrid renewable projects, pumped-storage hydroelectricity and demand-management systems are consequently becoming increasingly important components of India’s power infrastructure.

FDRE contracts provide renewable developers with a commercial incentive to build this flexibility directly into new projects rather than leaving the electricity grid alone to manage intermittency.

Storage Capacity Becoming an Important Part of Juniper’s Pipeline

Juniper’s own development portfolio illustrates how rapidly batteries are becoming integrated with large renewable plants.

As of late August 2026, the company reported approximately 503 MWh of operational battery capacity, but its total portfolio contained nearly 9 GWh of planned and operational BESS capacity when contracted and awarded projects were included.

This is a substantial shift from the traditional independent-power-producer model, where a developer might construct a solar or wind plant and simply sell the electricity generated.

Storage-backed projects require developers to manage charging cycles, forecast renewable generation, forecast electricity demand, determine optimal discharge periods and satisfy contractual power-delivery obligations.

Software and energy-management systems therefore become increasingly important alongside physical assets such as turbines, panels and batteries.

The transition makes renewable-energy companies progressively more similar to integrated power-system operators rather than pure owners of generation assets.

Battery Storage Can Reduce Renewable Curtailment

Battery storage also offers another important advantage by allowing electricity that might otherwise be curtailed to be retained.

During periods when renewable generation exceeds the grid’s immediate ability to absorb electricity, system operators may instruct plants to reduce production. This means potentially useful clean electricity is effectively lost.

A battery provides somewhere for at least part of that excess generation to go. Stored electricity can subsequently be returned to the grid when renewable output falls or demand increases.

At national scale, this capability could become increasingly valuable as India adds hundreds of gigawatts of renewable generation. Without adequate storage and transmission infrastructure, progressively larger mismatches could develop between periods of maximum renewable production and maximum electricity demand.

Projects combining oversised renewable generation with BESS capacity are one of the mechanisms being developed to close this gap.

177.6 MWp Now Commissioned From Planned 232.4 MWp

The latest commissioning provides a clear indication of the progress of Juniper Green Stellar’s 120-MW FDRE project.

Following the additional 12.4 MW of wind capacity, the company says commissioned generation has reached 177.6 MWp out of the planned 232.4 MWp, equivalent to roughly three-quarters of the planned renewable-generation capacity. The project also has approximately 201 MWh of battery storage associated with it.

The remaining generation capacity will further strengthen the ability of the system to produce sufficient renewable electricity across changing weather conditions while allowing the battery to shift part of that production into periods when contracted supply is required.

The project therefore demonstrates why installed renewable capacity in an FDRE plant can considerably exceed the amount of firm electricity sold under the PPA. The extra capacity provides the generation headroom required to compensate for the variable nature of renewable resources.

From Intermittent Renewable Energy to Power Available When Needed

The broader importance of the September 1 announcement lies less in the incremental 12.4 MW itself and more in the energy architecture into which that capacity is being integrated.

India’s first generation of large renewable projects demonstrated that solar and wind electricity could be developed rapidly and at increasingly competitive costs. The challenge now is to make that electricity more dependable, more controllable and more closely aligned with actual grid demand.

Wind-solar hybrid projects improve generation diversity, while batteries allow electricity to be shifted across hours. FDRE projects combine these technologies under contracts that require developers to provide a defined level of power rather than merely injecting intermittent renewable energy into the grid.

For Juniper Green Energy, the latest commissioning takes its overall operational portfolio to approximately 2,588 MWp and around 500 MWh of battery storage, while advancing a 120-MW contracted FDRE project towards completion.

More broadly, the project illustrates the direction in which India’s renewable-energy industry is moving. The next stage of the country’s clean-power expansion will not be defined only by how many solar panels and wind turbines are installed, but increasingly by whether renewable electricity can be stored, managed and delivered reliably at the precise times when India’s rapidly growing power system requires it.