The Board of IndianOil at its meeting held on 20th December 2021 has accorded approval for investment proposal of new crude oil pipeline system with nameplate capacity of 17.5 MMTPA from Mundra to Panipat alongwith with augmentation of crude oil tank farm at Mundra, at an estimated cost of Rs.9,028 crore. The project will meet the enhanced crude oil requirement arising out of capacity expansion of Panipat Refinery from 15 MMTPA to 25 MMTPA.
The project is expected to be completed within 36 months and would be synchronized with the commissioning of Panipat Refinery expansion project.
You may also like
-
ICAR Scientists Develop Indigenous Protective Gloves for Cotton Farmers, Sign Commercial Manufacturing Agreement
-
BHEL–Coal India Joint Venture Begins Construction of ₹25,016 Crore Indigenous Coal Gasification Project in Odisha
-
PM Modi to Inaugurate RBI’s Tier IV Data Centre and Cybersecurity Training Institute in Bhubaneswar
-
India Creates 11 Crore Digital Farmer IDs Five Months Ahead of Target, Strengthening AgriStack Infrastructure
-
Chak-Hao Black Rice of Manipur and Nagaland: The Aromatic Purple Heritage Grain with GI Recognition